10 and 11 Corporate Square
PROJECT DETAILS
Job Requirements
This project was a fast track complete renovation and addition to provide new office for the Center for Disease Control and Prevention. The project was performed for Choate Construction. Green Circle was selected because of our ability to provide a turn key solution. We performed roofing and other miscellaneous asbestos abatement, rigging and removal of pre-cast panels, selective structure demolition, and full interior demolition of all finishes. The project schedule required multiple crews working six days a week rain or shine. The weather was not cooperative, but we were able to maintain the schedule and deliver the shell on schedule and on budget.
Description of Work Performed
*Davis Bacon Wages
*40,000 SF of Asbestos Roofing Panels
*80,000 SF of Interior Finish Removal
*2 Steel Stairs/Elevator Removal
*Pre-Cast Panel Removal
*Selective Structural Steel Torching and Removal
*Recycling of Inert Debris (Concrete and Asphalt), Ferrous and Non-Ferrous Metals
*Project Size - $500,000 - $1,000,000